Car park resurfacing: a guide for managing agents
By Peter Priest, Director, Westway Asphalt · Updated
Survey first to find out whether the base is sound, write a short specification so quotes compare like for like, allow for leaseholder consultation where costs go through the service charge, and phase the work so residents and tenants can still park.
Start with a survey
Before pricing, find out whether the base is sound. Surface wear and fine cracks mean resurfacing will do. Dips, ruts, ponding and widespread potholes mean the base has failed in places. Where it isn't clear, trial holes or cores show the build-up, so contractors price the same work and you avoid surprises once the old surface is off.
Write a specification
Quotes are only comparable if everyone prices the same job. A short specification should set out:
- Areas to be resurfaced, and areas to be fully rebuilt
- Planing depths at kerbs, gullies and entrances, so levels stay the same
- The surface and binder course materials and thicknesses
- Drainage work: gullies, channels, falls
- Ironwork to be raised or replaced
- Line marking layout, including accessible bays
- Working hours, phasing and access to be kept open
We can write one for you, or price to yours.
Leaseholder consultation
If the car park belongs to a block of leasehold flats and the cost will be recovered through the service charge, check whether the works are qualifying works under section 20 of the Landlord and Tenant Act 1985. If any one leaseholder's contribution would be more than £250, the landlord must consult leaseholders before the work goes ahead, or risk not recovering the full cost. Allow time for this in the programme.
Phasing and access
- Split the car park into sections so part of it stays open each day
- Agree temporary parking, and keep disabled and emergency access throughout
- Give residents and tenants written notice with dates and times
- Consider early starts, evenings or weekends for busy commercial sites
Health and safety
Car park resurfacing is construction work, so the Construction (Design and Management) Regulations 2015 apply. Commercial clients have duties, including giving the contractor information about the site, such as underground services and known hazards. Ask for the contractor's risk assessments, method statements and insurance before work starts.
After the works
- Inspect the surface each year and repair potholes early
- Keep gullies and channels clear
- Re-mark bays when the lines fade, usually every few years
- Keep the specification and as-built details on file for next time
Questions
How long does car park resurfacing take?
Small car parks can often be done in a day or two; larger ones are phased over several days or weeks. The survey and phasing plan set the programme.
Should we resurface or rebuild?
Resurface where the base is sound; rebuild where it has failed. Most car parks need a mix, which a survey identifies.
Can you price to our specification?
Yes. Send it with the site plan, and we will price it line by line.