Padel court base specification
By Peter Priest, Director, Westway Asphalt · Updated
Based on LTA guidance, a UK padel court base is a free-draining, frost-resistant stone sub-base about 250 mm deep on average, with 65 mm of porous asphalt in two layers, laid flat or to a fall of no more than 1 in 100, ready for the ring beam, enclosure and turf.
Court size
A padel playing area is 20 m by 10 m, inside a glass and mesh enclosure. The base needs to extend under the whole court and the ring beam that the enclosure is fixed to, so it is set out from the court builder's drawings, not just the playing area.
The base build-up
LTA guidance for UK padel courts is a free-draining, non-frost-susceptible aggregate sub-base of about 250 mm average depth, with 65 mm of porous asphalt laid above it in two separate layers. The open structure lets rain drain straight through the turf, asphalt and stone, so the court is playable soon after rain.
| Typical padel base | |
|---|---|
| Formation | Excavated, trimmed and compacted, with soft spots replaced |
| Sub-base | Free-draining, frost-resistant stone, about 250 mm average depth |
| Binder course | Porous asphalt, first layer |
| Surface course | Porous asphalt, second layer; 65 mm total |
| Playing surface | Sand-dressed artificial turf, by the court builder |
Levels and tolerances
Padel bases are laid flat or to a gentle fall. LTA guidance allows a maximum single or dual-plane gradient of 1 in 100. Flatness matters as much as fall: any dip shows up in the bounce and holds water under the turf, so we check across the finished base with a straightedge before handing over.
Ring beam and enclosure
Most UK courts sit on a reinforced concrete ring beam, which the enclosure posts are bolted to. The LTA recommends the ring beam is designed by a structural engineer. Its top finishes level with the court construction, so the base contractor and court builder have to agree levels before anything is laid.
Order of works
- Court builder issues drawings and levels
- Excavation and formation
- Ring beam, where it is built before the base
- Sub-base laid and compacted
- Porous asphalt, two layers, laid and rolled
- Straightedge and level checks, then handover
- Enclosure, glass and turf by the court builder
Questions
Can a padel court go on an old tennis court?
Sometimes, if the existing base is sound, drains and is level enough. It needs checking: many old courts have heaved or settled.
Can you build bases under a canopy?
Yes. We built four padel court bases under a canopy at Club Langley in Beckenham.
Who builds the ring beam?
It varies by project: sometimes the base contractor, sometimes the court builder. It should be agreed and designed before work starts.