westway asphalt
Guide · Planning

Do you need planning permission for a tarmac driveway?

By Peter Priest, Director, Westway Asphalt · Updated

Short answer

Usually not. A tarmac driveway in the front garden of a house only needs planning permission if it covers more than 5 m² and rainwater runs off it rather than draining on your own land. Lay it porous, or drain it to a lawn, border or soakaway, and you don't need to apply.

The rule in one paragraph

Since 1 October 2008, laying a new or replacement hard surface of more than 5 square metres in the front garden of a house in England has only been permitted development, meaning no application is needed, if the surface is permeable or the water from it drains to a permeable area on your property. If neither is true, you need planning permission. The front garden means the land between the front wall of the house and the road.

The rule exists because paved front gardens send rainwater straight into drains and onto roads, which adds to surface flooding. That is why it is about where the water goes, not what the driveway looks like.

What counts as permeable

Government guidance gives three routes: gravel or a mostly planted area; directing water from a hard surface to a border, rain garden or soakaway; or a permeable surface such as permeable block paving or porous asphalt. In practice, these are the options for a driveway:

Porous asphalt

Open-graded asphalt that lets water straight through into a stone base.

Permeable block paving

Blocks with gaps filled with grit, laid on an open-graded base.

Gravel

Loose stone, though some councils restrict it near the pavement.

Impermeable surface, drained on site

Standard tarmac or concrete laid to fall into a lawn, border, rain garden or soakaway on your property.

The base matters as much as the top. Ordinary MOT Type 1 sub-base contains fine material that stops water draining, so permeable driveways sit on open-graded stone such as Type 3 or 4/20, which holds water while it soaks away.

How to lay tarmac without needing permission

There are two ways to have an asphalt driveway and stay within the rules:

  • Porous asphalt on an open-graded stone base. Water goes straight through, so the driveway can be any size.
  • Standard tarmac laid to fall towards a lawn, planted border or rain garden, or into a channel drain that feeds a soakaway on your land. The water has to stay on your property, not run onto the pavement.

Which is better depends on your garden. If there is planting next to the drive, falls to the border are simple and cheap. If the whole frontage is being used for parking, porous asphalt is usually the neater answer. On heavy London clay, either way needs the base or soakaway sized properly, because water soaks in slowly.

When you always need permission

Even a fully permeable driveway can need planning permission in these cases:

  • Flats and maisonettes: permitted development rights for hard surfaces cover houses only
  • Listed buildings: you need listed building consent for works that affect the building's setting
  • Article 4 areas: some conservation areas have removed permitted development rights
  • A new access onto a classified road, which needs planning permission before a dropped kerb
  • Taking down a front wall over 1 m high next to the road in a conservation area

Your council's planning team can confirm whether any of these apply. Our borough pages list the main local rules for each council we cover.

Rules by borough

Dropped kerbs are a separate approval

Planning permission and a dropped kerb are two different things. To drive across the pavement you need a vehicle crossover, approved and built by your council as highway authority, even if the driveway itself needs no planning permission. Each London council sets its own minimum parking space, fees and rules.

How to get a dropped kerb in London

If your driveway is already laid

If an impermeable driveway over 5 m² was laid after October 2008 without permission or on-site drainage, the council can ask for a retrospective planning application. Often the simplest fix is to add drainage: a channel drain across the low end feeding a soakaway, or cutting in a planted strip for water to run into. We can survey an existing driveway and suggest the least disruptive option.

Questions

Does the 5 m² rule apply to replacing an old driveway?

Yes. The rule covers new and replacement hard surfaces in a front garden. Repairing a small area, such as patching potholes, isn't the same as replacing the driveway.

Is tarmac permeable?

Standard tarmac isn't: it is dense and sheds water. Porous asphalt is a different mix with no fine material, so water passes through it. Both look like a dark asphalt driveway.

Does the rule apply to back gardens and side drives?

The 5 m² rule is about front gardens, meaning the land between the front of the house and the road. Other permitted development limits can still apply elsewhere.

Do I need planning permission for a dropped kerb?

The dropped kerb needs your council's highways approval, which is separate from planning. Planning permission is also needed first on classified roads and in some other cases set by each council.

When did the rule come in?

1 October 2008, for houses in England.

Where can I check the official guidance?

The government's 'Guidance on the permeable surfacing of front gardens' and the Planning Portal both explain the rule. Your council's planning team can confirm it for your property.

Planning a new driveway?

We design every driveway to stay within the planning rules, and check your council's dropped kerb rules at the survey.

Get my free quote
Get a free quote